9/19/2000, MURRAY, Ut - Pentalon Construction is the general contractor for the POL Truck Parking and Containment facility being built for the Utah Air National Guard. The project is located at 765 North 2200 West in Salt Lake City, Utah. Project design and engineering was provided by 151 CES of the Air National Guard Civil Engineering division.
The project consists of the construction of four parking bays for refueling trucks and installation of a underground oil/water separator; above ground storage tank; related pumps, piping and mechanical controls; system startup and testing. The construction duration of the project is 90 days. The contract amount for the project is $149,991.
The project broke ground on Monday, September 18, 2000.
The project manager is George Parker and the project superintendent is John Simler.
Subcontractors and suppliers for the project include: Staker Paving and Enviro Reps, Inc. Pentalon Construction will provide the remaining construction services. |
 |
|
|
|
|
|
|
ABOUT PENTALON CONSTRUCTION |
 |
|
|
|
|
|
|
Pentalon Construction performs over $30 million in work annually. The company is known as a leader in building apartment and condominium complexes along with commercial construction. With it's highly skilled workforce, Pentalon provides site and structural construction services throughout the intermountain west. For more information about Pentalon Construction or projects they are working on visit them on the World Wide Web at www.pentalonconstruction.com |
 |
|
|
|
|
|
|